Late, Early, Not Yet.

Tesla has shown nine vehicles with a date attached. We measured each one against the first date it was promised, then did the same for eleven years of self-driving forecasts.

2 November 2026 · 7 min read

Smnt / CC BY-SA 4.0

Tesla has shown nine vehicles with a date attached. Each time, the company or Elon Musk said when the first customers would have one. We took the first date given for each, and checked it against the day the first one was handed over.

Then we did the same for eleven years of self-driving forecasts, and for the delivery targets Tesla sets each January. One of the three is far more reliable than the others.

The Cybertruck concept driving in the dark after its 2019 unveiling, its light bar glowing across the front.

01 · The vehicles

Nine cars,three dates each.

When each was unveiled, the first date Tesla gave for it, and its first delivery. Scroll, and the same nine lines are measured three ways.

Cybertruck, unveiling night, 2019. u/Kruzat / CC BY-SA 4.0

Calendar

Nine vehicles on one calendar. Each line starts at the unveiling (○), passes the date first promised (|) and stops at the first delivery (●). One still runs on to today.

From the unveiling

Line them up at their unveilings. The Model Y took twelve months from stage to first customer. The Semi took five years. The second Roadster is at almost nine years and counting.

From the promise

Now line them up at the promise. Red is time past it. Five arrived late: the first Roadster by four months, the Model S by six, the Model X by 17, the Cybertruck by 23 and the Semi by 35.

Early

Blue is time to spare. Three beat the date, each with a footnote: the first 30 Model 3s went to employees, the Model Y arrived nine months inside “fall 2020”, and the Cybercab carries Robotaxi riders but is not yet sold.

Not yet

One line never closes. The second-generation Roadster was promised for 2020. It is 70 months late and counting.

The typical gap

Across the eight that have arrived, the typical Tesla reached its first customer five months after the date first promised.
Nine Tesla vehicles: unveiling, first promise, first delivery
First promise
Roadster (2006 · first gen)19 July 2006Deliveries “expected to begin next summer”End of summer 2007February 2008418
Model S (2009)26 March 2009Production expected to start in “late 2011”31 December 201122 June 2012639
Model X (2012)9 February 2012Production in late 2013, significant deliveries in “early 2014”30 April 201429 September 20151744
Model 3 (2016)31 March 2016Deliveries to begin “late 2017”31 December 201728 July 2017-516
Roadster (2017 · second gen)16 November 2017Available in 2020, from US$200,00031 December 2020Not yet70108
Semi (2017)16 November 2017Production to begin in 201931 December 20191 December 20223560
Model Y (2019)14 March 2019First deliveries in “fall 2020”21 December 202013 March 2020-912
Cybertruck (2019)21 November 2019Production “expected to begin in late 2021”31 December 202130 November 20232348
Cybercab (2024)10 October 2024In production in 2026, “before 2027”31 December 20263 September 2026-423

First, the stage.

Each was shown, with a date, before anyone could buy one.

  • Roadster
  • Model S
  • Model X
  • Model 3
  • Cybertruck
  • Cybercab

01a · Late

The typical Teslaarrived five months late.

Tesla’s first car set the tone. At its unveiling in a Santa Monica hangar in July 2006, the company said Roadster deliveries were expected to begin the next summer. The first production car went to Elon Musk, then chairman, in February 2008, about four months after that summer ended. Its two-speed gearbox was part of the trouble; the first cars shipped with an interim transmission.

A Tesla Roadster validation prototype on show in February 2008.
February 2008, the month the first production Roadster arrived in America. Its owner was the chairman.Steve Jurvetson / CC BY 2.0

Since then the gap has wandered. The Model S reached its first owners on 22 June 2012, six months after its late-2011 production target. The Model X, shown in February 2012 with deliveries promised for early 2014, took a further seventeen months. The Cybertruck ran 23 months past “late 2021”.

The Semi, promised for 2019, reached PepsiCo on 1 December 2022. Tesla says volume production began only this year, at a Nevada factory it opened in September.

A Tesla Semi in PepsiCo livery hauling a trailer on a California road.
A stainless-steel Cybertruck Foundation Series at dusk in San Jose.
A Tesla Model X with both falcon-wing doors raised.
Inside the cab of the Tesla Semi prototype: a central driving seat between two touchscreens.
A silver Tesla Semi tractor unit parked on a street outside Tesla headquarters.

35 months, for the Semi.

The late ones: Semi, Cybertruck, Model X.
  1. An orange first-generation Tesla Roadster with a black roof, side-on.
    2006

    Roadster, first generation

    4 months late.

    Deliveries “expected to begin next summer”. First production car to Elon Musk, then chairman. Regular production from March 2008.

    Unveiled
    19 July 2006
    Promised
    End of summer 2007
    First delivery
    February 2008

    Eugene Zelenko / CC BY-SA 4.0

  2. A white Tesla Model S, front three-quarter.
    2009

    Model S

    6 months late.

    Production expected to start in “late 2011”. Production ended at Fremont on 10 May 2026.

    Unveiled
    26 March 2009
    Promised
    31 December 2011
    First delivery
    22 June 2012

    Tokumeigakarinoaoshima / CC0

  3. A white Tesla Model X, front three-quarter.
    2012

    Model X

    17 months late.

    Production in late 2013, significant deliveries in “early 2014”. Rescheduled to late 2014, then to Q3 2015. Production ended 10 May 2026.

    Unveiled
    9 February 2012
    Promised
    30 April 2014
    First delivery
    29 September 2015

    Alexander Migl / CC BY-SA 4.0

  4. A red Tesla Model 3 prototype, front three-quarter.
    2016

    Model 3

    5 months early.

    Deliveries to begin “late 2017”. First 30 cars to Tesla employees. The US$35,000 version went on sale on 28 February 2019.

    Unveiled
    31 March 2016
    Promised
    31 December 2017
    First delivery
    28 July 2017

    Steve Jurvetson / CC BY 2.0

  5. A red second-generation Roadster prototype with its roof panel raised.
    2017

    Roadster, second generation

    Not yet: 70 months and counting.

    Available in 2020, from US$200,000. Shown again on 15 October 2026. Musk now says production starts in 2028.

    Unveiled
    16 November 2017
    Promised
    31 December 2020
    First delivery
    Not yet

    Steve Jurvetson / CC BY 2.0

  6. A silver Tesla Semi hauling a trailer.
    2017

    Semi

    35 months late.

    Production to begin in 2019. First trucks to PepsiCo. Tesla says volume production began in 2026, at a Nevada factory opened in September.

    Unveiled
    16 November 2017
    Promised
    31 December 2019
    First delivery
    1 December 2022

    Korbitr / Public domain

  7. A white Tesla Model Y, front three-quarter.
    2019

    Model Y

    9 months early.

    First deliveries in “fall 2020”. Moved forward to summer 2020 in October 2019, then delivered in March.

    Unveiled
    14 March 2019
    Promised
    21 December 2020
    First delivery
    13 March 2020

    Alexander Migl / CC BY-SA 4.0

  8. A stainless-steel Cybertruck with bullet dents in its door.
    2019

    Cybertruck

    23 months late.

    Production “expected to begin in late 2021”. Slipped to late 2022, then 2023. A first batch of about ten trucks handed over at Giga Texas.

    Unveiled
    21 November 2019
    Promised
    31 December 2021
    First delivery
    30 November 2023

    TaurusEmerald / CC BY-SA 4.0

  9. A gold two-seat Cybercab, side-on.
    2024

    Cybercab

    4 months early.

    In production in 2026, “before 2027”. Production began at Giga Texas in April 2026. First Robotaxi rides in Cybercabs in Austin. Not yet sold; Tesla is aiming for first customer deliveries by the end of 2026.

    Unveiled
    10 October 2024
    Promised
    31 December 2026
    First delivery
    3 September 2026

    Daniel Lu / CC BY-SA 4.0

01b · Early

Three came early,each with a footnote.

The first 30 Model 3s were handed over on 28 July 2017, five months before the “late 2017” Tesla had given, though all 30 went to employees and the US$35,000 version did not go on sale until February 2019. The Model Y, promised for fall 2020, was in customers’ hands by March 2020. The Cybercab, which Musk said would be in production in 2026, began carrying Robotaxi riders in Austin on 3 September 2026.

Early, sort of.

Employees first for the Model 3. Riders, not buyers, for the Cybercab.

  • Model 3
  • Cybercab
  • Fremont
  • Austin

Nine vehicles, four numbers

Median gap between promise and first delivery, across the eight vehicles delivered
5 mo
Arrived before the promised date: Model 3, Model Y and Cybercab
3 of 8
The longest wait that has ended, for the Semi
35 mo
And counting, for the second Roadster, promised for 2020
70 mo

02 · Not yet

Promised for 2020.Now, 2028.

The second-generation Roadster is the one line on the chart that never closes.

A red second-generation Tesla Roadster prototype with its roof panel raised.
2020Roadster, second generation · promised from US$200,000Steve Jurvetson / CC BY 2.0

The second-generation Roadster rolled out of the back of a Semi trailer on 16 November 2017, priced from US$200,000 and promised for 2020. On 15 October 2026 Tesla showed it again, at a SpaceX test site in Texas, and Musk said production would start in 2028. Reservations reopened, with a US$50,000 deposit.

Second Roadster · 2 November 2026

70 months

Past the end of 2020, the date it was first promised for. No customer has one.

Two of these cars have already left the line. The last Model S and Model X were built at Fremont on 10 May 2026, after nearly fourteen and eleven years on sale. Tesla is converting the space to build its Optimus robot.

The S and the X, 2012 to 2026.

The last ones were built at Fremont on 10 May 2026.

  • Model S
  • Model X
  • Fremont
  • Optimus
A driver’s view from a Model X in traffic, the dashboard showing Autopilot engaged.

03 · Self-driving

About a year away,for eleven years.

Twelve dated forecasts, made in public by Musk or Tesla between 2015 and 2026.

Ian Maddox / CC BY-SA 4.0

A car has a delivery date you can check. Self-driving is harder to pin down, because the goal keeps changing shape: complete autonomy, a coast-to-coast demonstration, “feature complete”, a million robotaxis, “safer than human”, unsupervised rides.

Here are twelve dated forecasts made in public by Musk or Tesla between 2015 and 2026, plotted by when each was said against when it was due. A forecast due on the day it was made would sit on the diagonal. They all sit a short hop above it.

Median lead time

9 months

Between a self-driving forecast and its deadline. Ten have fallen due; one has arrived, seven months late.

Fig. 1 · Always next year

Every forecast was due within about two years. Nine were missed.

Twelve self-driving forecasts. Across: when it was said. Up: when it was due. A red line climbs from each missed deadline to today.

“This year” is read as 31 December of that year; “next year” as 31 December of the following year; “approximately two years” from December 2015 as December 2017. Only one forecast has a dated outcome: unsupervised rides in Austin, due in June 2025, began on 22 January 2026. Numbers match the list below.
Twelve self-driving forecasts
Every forecast was due within about two years. Nine were missed.
Forecast
0121 December 2015Complete autonomy in about two years31 December 201724Missed
0219 October 2016Los Angeles to Times Square, hands off31 December 201714Missed
0319 February 2019Feature complete31 December 201910Missed
0422 April 2019A million robotaxis31 December 202020Missed
059 July 2020Level five basics31 December 20206Missed
0627 January 2021Better than human31 December 202111Missed
0726 January 2022“Shocked” if not31 December 202211Missed
0819 July 2023The boy who cried FSD31 December 20235Missed
0929 January 2025Austin, no one aboard30 June 20255Arrived 22 January 2026
1023 July 2025Half the US31 December 20255Missed
1118 May 2026“Widespread”31 December 20267Open
1221 October 2026Owners join, Q2 202730 June 20278Open

  1. 0121 Dec 2015Fortune interview

    I think we will have complete autonomy in approximately two years.

    MissedOwners’ cars still need a supervising driver.
  2. 0219 Oct 2016Tesla press call

    A fully autonomous drive from a home in Los Angeles to Times Square by the end of next year.

    MissedThe demonstration drive never took place.
  3. 0319 Feb 2019ARK Invest podcast

    I think we will be feature complete, full self-driving, this year.

    Missed
  4. 0422 Apr 2019Autonomy Day

    Next year, for sure, we will have over a million robotaxis on the road.

    MissedTesla’s first Robotaxi rides came in June 2025.
  5. 059 Jul 2020World AI Conference, Shanghai

    I remain confident that we will have the basic functionality for level five autonomy complete this year.

    Missed
  6. 0627 Jan 2021Q4 2020 results call

    Musk said he was highly confident the car will be able to drive itself with reliability in excess of human this year.

    Missed
  7. 0726 Jan 2022Q4 2021 results call

    I would be shocked if we do not achieve full self-driving safer than human this year.

    Missed
  8. 0819 Jul 2023Q2 2023 results call

    I know I’m the boy who cried FSD, but man, I think we’ll be better than human by the end of this year.

    Missed
  9. 0929 Jan 2025Q4 2024 results call

    An initial paid launch of unsupervised, no one in the car, full self-driving in Austin in June.

    7 months lateOpened 22 June 2025 with a safety monitor on board. First rides with no one in the car: 22 January 2026.
  10. 1023 Jul 2025Q2 2025 results call

    Autonomous ride-hailing for probably half the population of the US by the end of the year, subject to regulatory approval.

    Missed
  11. 1118 May 2026Smart Mobility Summit, by video

    Driverless operation probably will be widespread in the U.S. by end of this year.

    OpenDue 31 December 2026.
  12. 1221 Oct 2026Q3 2026 results call

    Ashok Elluswamy, Tesla’s head of AI software, on owners’ cars joining the Robotaxi fleet inside its service areas: We suspect somewhere around Q2 next year.

    OpenDue 30 June 2027.

What did arrive is real, and narrower than the forecasts. FSD (Supervised), the version owners buy, still needs a driver watching at all times. Tesla’s Robotaxi service opened in Austin on 22 June 2025 with an employee in the front passenger seat. On 22 January 2026 Musk posted that rides had begun there with no safety monitor in the car, mixed in with monitored ones. Cybercabs, with no steering wheel or pedals, joined the Austin fleet in September.

What did arrive.

Supervised driving for owners, and a small driverless fleet in Austin.

A driver’s view from a Model X in traffic, the dashboard showing Autopilot engaged.
SupervisedHands near the wheelFSD (Supervised), the version owners buy, still needs a driver watching at all times.Ian Maddox / CC BY-SA 4.0
Tesla’s Full Self-Driving computer board, with two large chips.
HardwareThe self-driving computerThe board that runs Tesla’s driver-assistance software.Votpuske / CC BY 4.0
Looking into the Cybercab cabin: two pale seats and a screen, with no steering wheel or pedals.
September 2026No wheel, no pedalsCybercabs joined the Austin Robotaxi fleet in September.Dllu / CC BY-SA 4.0
A gold Tesla Cybercab driving on Interstate 280 near Palo Alto.
AustinRobotaxiRides with no safety monitor began on 22 January 2026, mixed in with monitored ones.Daniel Lu / CC BY-SA 4.0

Musk knows the pattern. On the July 2023 call he prefaced that year’s forecast with a joke at his own expense.

Elon Musk on stage at Tesla’s 2015 annual meeting.

I know I’m the boy who cried FSD, but man, I think we’ll be better than human by the end of this year.

Elon MuskTesla Q2 2023 results call, 19 July 2023

04 · Deliveries

On volume,it mostly does what it says.

The numbers Tesla gives each January are a different kind of promise, and a far more reliable one.

Red robot arms working on car bodies along the Tesla assembly line.
Steve Jurvetson / CC BY 2.0

In the six years Tesla named a firm figure or range for annual deliveries, it finished within 10% of the bottom of it every time, and four times within about two per cent.

Fig. 2 · Guidance

Six annual targets, all within 10%

Full-year deliveries as a share of the low end of Tesla’s guidance for that year.

Guidance as first given for the year: 2014 “over 35,000” Model S (cut to about 33,000 in November 2014), 2015 50,000–55,000, 2016 80,000–90,000, 2019 360,000–400,000, 2020 500,000, 2023 about 1.8 million. Tesla gave no firm number in other years.
Annual guidance and deliveries
Six annual targets, all within 10%
2014over 35,000 Model S31,65590%
201550,000–55,00050,580101%
201680,000–90,00076,23095%
2019360,000–400,000367,500102%
2020500,000499,55099.9%
2023about 1.8 million1,808,581100.5%

2020 is the famous one. Tesla had been aiming for half a million cars a year by 2020 since its Gigafactory plans of 2014, and kept the target after the pandemic shut its Fremont factory for about seven weeks.

Elon Musk on stage describing the Gigafactory in front of a projected slide.
Musk describing the Gigafactory. The half-million target was set alongside it.Steve Jurvetson / CC BY 2.0

2020 · target 500,000

499,550

Cars delivered in 2020: 450 short of half a million.

The long-range aim fared worse. From January 2021 Tesla told investors it expected “50% average annual growth in vehicle deliveries” over a multi-year horizon. For three years it ran ahead of that pace. Then growth stopped. Deliveries slipped in 2024, for the first time in Tesla’s history, and fell 9% in 2025. In May 2024 the goal of 20 million cars a year by 2030 dropped out of Tesla’s impact report.

Fig. 3 · Deliveries

Ahead of the 50% path for three years, then flat

Vehicles delivered each year, 2012 to 2025, and January to September 2026. Dashed line: 50% annual growth from 2020, Tesla’s stated aim from January 2021.

Totals are the figures Tesla first announced for each year; Tesla says final numbers can vary by up to 0.5%. 2017 is about 103,000, and 2012 is approximate (about 2,650 Model S). 2026 is split into Q1 358,023, Q2 480,126 and Q3 486,532.
Tesla deliveries by year
Ahead of the 50% path for three years, then flat
2012about 2,650–
201322,477+748.2%
201431,655+40.8%
201550,580+59.8%
201676,230+50.7%
2017about 103,000+35.1%
2018245,240+138.1%
2019367,500+49.9%
2020499,550+35.9%
2021936,172+87.4%
20221,313,851+40.3%
20231,808,581+37.7%
20241,789,226-1.1%
20251,636,129-8.6%
2026 (Jan–Sep)1,324,681+8.8% on Jan–Sep 2025

2026 has turned back up. Tesla delivered 1,324,681 vehicles in the first nine months, 8.8% more than in the same stretch of 2025.

2026 so far

Vehicles delivered, January to September 2026
1,324,681
On the same nine months of 2025
+8.8%
Delivered in the third quarter, the best of the three
486,532

Where the volume comes from.

The factories and the network behind the January numbers.

Rows of new Teslas waiting for pickup at the Fremont factory.
Fremont, CaliforniaWhere it startedThe S and X were built here for nearly fourteen and eleven years.Steve Jurvetson / CC BY 2.0
Tesla’s Gigafactory in the Nevada desert, December 2019.
NevadaThe GigafactoryPlanned in 2014, alongside the aim of half a million cars a year by 2020.Smnt / CC BY-SA 4.0
Tesla’s Gigafactory Texas near Austin, June 2022.
Austin, TexasGiga TexasThe first Cybertrucks were handed over here. Cybercab production began here in April 2026.Larry D. Moore / CC BY 4.0
A Tesla Semi in PepsiCo livery hauling a trailer on a California road.
On the roadThe SemiFirst trucks to PepsiCo in December 2022; volume production in 2026.Dllu / CC BY-SA 4.0
Four Tesla Supercharger stalls in Inyokern, California.
EverywhereSuperchargersFour charging stalls in Inyokern, California.Daniel Lu / CC BY-SA 4.0

05 · Still open

Four datesto check next.

These are the deadlines on the table as of today, each set by Tesla or Musk in the past six months. Two fall due before New Year.

Fig. 4 · Next

The next deadlines

Read as generously as the wording allows. Days counted from 2 November 2026.

  1. 59 daysBy 31 Dec 2026Driverless rides “widespread” in the USMusk, May 2026
  2. 59 daysBy 31 Dec 2026First Cybercabs sold to customersTesla, October 2026
  3. 240 daysBy 30 Jun 2027Owners’ cars join the Robotaxi networkTesla, October 2026
  4. 790 daysBy 31 Dec 2028Second Roadster in productionMusk, October 2026

Two fall due before New Year.

Driverless rides “widespread” in the US, and the first Cybercabs sold to customers. Both by 31 December 2026.

Steve Jurvetson / CC BY 2.0

Pictures 46

  1. Tesla roadster 2020 prototypeSmnt · CC BY-SA 4.0
  2. Introducing the Tesla (50857400348)Steve Jurvetson from Los Altos, USA · CC BY 2.0
  3. The Architects (3391675968)Steve Jurvetson from Los Altos, USA · CC BY 2.0
  4. The Tesla has landed - Flickr - jurvetsonSteve Jurvetson from Los Altos, USA · CC BY 2.0
  5. Tesla Roadster Sport-1Eugene Zelenko · CC BY-SA 4.0
  6. 20100715-elon-musk-tesla-roadster-tsla-10einstraus from Vancouver, Canada · CC BY-SA 2.0
  7. Tesla Model S at NAIAS 2012 (6672639131)Autoviva · CC BY 2.0
  8. Tesla Model S first deliveriesFlickr user jurvetson (Tim Draper/Steve Jurvetson) · CC BY 2.0
  9. 2012-06-01-tesla-headquarters-group-photo-s1Steve Jurvetson · CC BY 2.0
  10. Tesla Factory, Fremont (CA, USA) (8765031876)Maurizio Pesce from Milan, Italia · CC BY 2.0
  11. Tesla MODEL S frontTokumeigakarinoaoshima · CC0
  12. Sliding inside the Tesla Model X (6849378716)Steve Jurvetson from Los Altos, USA · CC BY 2.0
  13. Tesla Model X P100DLTurnstange · CC BY-SA 4.0
  14. Tesla Model X 100D 1X7A6736Alexander Migl · CC BY-SA 4.0
  15. Candy Red Tesla Model 3 trimmedCandy Red Tesla Model 3.jpg: Steve Jurvetson derivative work: Mariordo (Mario Roberto Durán Ortiz) · CC BY 2.0
  16. Tesla Model X and Model 3 at the unveiling eventSteve Jurvetson · CC BY 2.0
  17. First flotilla of Model 3 carsSteve Jurvetson · CC BY 2.0
  18. First Model 3 production cars ready for deliverySteve Jurvetson · CC BY 2.0
  19. The Model 3 InteriorSteve Jurvetson · CC BY 2.0
  20. Tesla Model 3 trimmed retouchedSteve Jurvetson · CC BY 2.0
  21. The Tesla Semi Truck (40705940423)Steve Jurvetson from Menlo Park, USA · CC BY 2.0
  22. Tesla Semi Pepsi 2023-10-31-13-39-37 DSCF2583 dlluDllu · CC BY-SA 4.0
  23. Tesla Semi cockpitSteve Jurvetson · CC BY 2.0
  24. Tesla Model Y 1X7A6211Alexander Migl · CC BY-SA 4.0
  25. Tesla Cybertruck damaged windowu/Kruzat · CC BY-SA 4.0
  26. 20191121-tesla-cybertruck-driving-lightbaru/Kruzat · CC BY-SA 4.0
  27. Foundation series Cybertruck at dusk in San Jose dlluDllu · CC BY-SA 4.0
  28. Tesla Cybercab at Santana Row side view dlluDllu · CC BY-SA 4.0
  29. Tesla Cybercab on Interstate 280 near Palo Alto dlluDaniel Lu (User:dllu) · CC BY-SA 4.0
  30. Tesla Cybercab at Santana Row interior dlluDllu · CC BY-SA 4.0
  31. Front of the Tesla CybercabSteve Jurvetson from Los Altos, USA · CC BY 2.0
  32. Tesla ASM Lineup of VehiclesSteve Jurvetson · CC BY 2.0
  33. Tesla Autopilot Engaged in Model XIan Maddox · CC BY-SA 4.0
  34. Tesla Full Self-Driving computerVotpuske · CC BY 4.0
  35. Elon Musk at the 2015 Tesla Motors Annual Meeting (18659265152)Steve Jurvetson from Los Altos, USA · CC BY 2.0
  36. Elon Musk describing the Tesla Gigafactory (14162156679)Steve Jurvetson from Los Altos, USA · CC BY 2.0
  37. Tesla Gigafactory 1 - December 2019Smnt · CC BY-SA 4.0
  38. Gigafactory Texas Building 1 June 2022Larry D. Moore · CC BY 4.0
  39. New Teslas at the factorySteve Jurvetson · CC BY 2.0
  40. Tesla Motors Assembly Line (6858583426)Steve Jurvetson from Los Altos, USA · CC BY 2.0
  41. Tesla auto botsSteve Jurvetson · CC BY 2.0
  42. Optimus bot at Tesla showroom - 20251118 - 01Sikander · CC BY-SA 4.0
  43. Tesla Supercharger Inyokern California 2026 dlluDaniel Lu (User:dllu) · CC BY-SA 4.0
  44. Tesla Roadster 2.0 (47619421652)Steve Jurvetson from Menlo Park, USA · CC BY 2.0
  45. Tesla Cybertruck Bulletproof Test Petersen Automotive MusemTaurusEmerald · CC BY-SA 4.0
  46. Tesla Semi 3Korbitr · Public domain

Cite this

The Studio (2026). “Late, Early, Not Yet.” No. 003, published 2 November 2026. thestudio.nz/drops/tesla-promises